Minutes of negative delivery of the works

MUNICIPALITY OF …………

PROVINCE OF …………

Works of …………

Company: ............

Contract date ............ rep. No. ............ registered at ............ on ............

Contractual amount of the works euro ......... net of the auction reduction of .......%

MINUTES OF NEGATIVE DELIVERY OF WORK

The day ……. of the month ………. of the year two thousand ........., the undersigned .................. as construction manager

Given the contract dated …… .., repertoire no.… .., registered at ……………. on ……………. at n ° ............, considering that the Head of the procedure, with note prot. n. …………. on ………… it ordered the delivery of the works;

Having regard to Article 154, paragraph 7 of Presidential Decree 207/2010,

the undersigned …………… Construction manager, after notice sent to the Contractor with prot. n. ………. on ............ .., it was agreed on the place where the works are to be carried out, in the presence of the Lords:

- ……………… .;

- ……………… .;

- ……………… .;

Due to the absence of the contractor, however, he was unable to proceed with the delivery of the works.

The undersigned director therefore provides:

- to postpone the delivery to the day .........

- to invite Mr. ………………… owner / legal representative of the company to the Technical Office ………………………… .. to proceed with the delivery of the aforementioned works.

The undersigned director also remembers:

- that the starting date of the contractual term remains that of the date of the first call (Article 153, paragraph 7 of Presidential Decree 207/2010);

- that if the contractor does not show up, a further report will be drawn up and that the contracting authority will have the right to terminate the contract and forfeit the deposit.

A copy of this report is sent to the company by registered letter with return receipt.

The construction manager

Visa: The person in charge of the procedure