Calculation of men day - incidence of labor

Calculation of men day - incidence of labor

Calculation of the man days and the obligations to be carried out for the individual construction site, based on the amounts of the work categories - Performs the calculation of the incidence of labor for each individual process (Ministerial Decree 11/12/1978) - Filling in the fields automatically indicates whether preliminary notification, the appointment of Coordinators and the drafting of the PSC (Safety and Coordination Plan) are necessary.

This program designed and implemented by Itieffe represents a very useful tool for companies and organizations involved in project planning and management, especially in sectors such as construction, industry, agriculture and other activities that require the mobilization of manpower for specific periods. This tool allows you to precisely calculate the number of man-days needed to complete a specific job or project, considering various variables related to manpower. Before examining the specific content of the program, it is important to provide a background to understand the context and importance of this resource.

Workforce management context:

Manpower management is a critical aspect of planning and executing any project. Correctly calculating the number of workers needed and the associated work days is critical to ensuring timely and efficient completion of project activities.

Influence of labor on costs and times:

Labor is one of the main production costs in many economic activities. Its impact on the total costs and duration of the project is significant. Accurate man-day calculation is essential to effectively manage budgets and meet delivery times.

Importance of the “man-day calculation” program:

This program is important for several reasons:

  1. Efficient planning: allows detailed planning of the necessary manpower, avoiding overcrowding or underutilization of human resources.
  2. Cost control: Helps keep labor costs under control, allowing for more accurate budget management.
  3. On time: helps to respect delivery times and avoid delays in completing the project.
  4. Resource optimization: promotes the optimization of human resources, assigning the necessary personnel for each phase of the work.

Program content:

The “Man-Day Calculation – Labor Incidence” program includes:

  • Calculation tools based on specific parameters of the project, such as the description of the processes, the amount of the category of work and the unit cost of labor based on the specialization of the workers.

In conclusion, this program is an essential tool for efficient project planning and management, ensuring correct allocation of human resources and better cost and time management. Its adoption helps improve the operational efficiency and competitiveness of companies in a wide range of industrial sectors.

Calculation of men day - incidence of labor

Calculation of the man-days and the formalities to be done for the single site, based on the amounts of the categories of work

Calculate the incidence of manpower for each individual process by referring to the Ministerial Decree 11/12/1978.

By filling in the fields, it automatically indicates whether the preliminary notification is required, the appointment of the Coordinators, the drafting of the PSC (Safety and coordination plan).

Instructions

Like all our programs, the procedure for calculating the day men is quite intuitive.

Here's an example:

Let's start entering the characteristic data of the construction site:

1 - client, CSP, etc .;

2 - percentage general expenses and business profits, (values ​​which can also be varied);

3 - enter the description of the work (drop-down menu prepared with the percentage tables of incidence for the main categories of work listed in the Ministerial Decree 11/12/1978) and the amounts of the same;

4 - enter the number of self-employed workers and that of companies. The number of annual working days is usually the one indicated;

5 - the program automatically calculates the required obligations;

6 - by inserting the expected average number of workers, the number of man-days and other relevant parameters can be traced.

Now let's analyze the conformation of the typical team:

1 - in this box the number of men needed is calculated according to the type of work and the daily cost of a typical team;

2 - here is the cost of labor per job, taken from the price list;

3 - indication of which price list is used;

4 - total daily cost for all types of processing.

Easy?

good job

Other free programs of the same kind offered by itieffe ▼

Calculation of men day - incidence of labor

The program below is free to use.