MUNICIPALITY OF …………
PROVINCE OF …………
Works of …………
Company: ............
Contract date ............ rep. No. ............ registered at ............ on ............
Contractual amount of the works euro ......... net of the auction reduction of .......%
Coordination and cooperation report
On the day ............ of the month ............ of the year two thousand ............, upon notice with a note ............ of ............, the undersigned meet:
………… construction manager;
………… coordinator for the execution of the works;
………… legal representative of the company;
………… supervisor;
………… responsible for the Contractor's Prevention and Protection Service;
………….
Since art. 26, paragraph 3, of Legislative Decree 81/2008 provides for cooperation in the implementation of measures to prevent and protect against risks at work;
Since art. art. 26, paragraph 3, of Legislative Decree 81/2008 provides for the implementation of the coordination of measures to protect and prevent the risks to which workers are exposed;
All those present agree that to perform in complete safety and in compliance with the aforementioned regulations, carry out the following operations:
- location of the work areas and routes to access them:
...............................................................
- estimated duration of the works:
........................................................................
- any possible interference:
……………………………………………………………
- protective and preventive measures to be taken:
..................................................................
Of which this report is drawn up which, after reading and confirmation, is signed by the attendees.